Skip to Content

Module 5: Diagnostics, Troubleshooting & Maintenance

Module 5: Diagnostics, Troubleshooting & Maintenance

24 sept. 2026

Module information


Audience

Applicants to the EcoStride Installation Partner Programme

Study time

About 2 hours

Units

11

Assessment

Part 1, Segment 5 (10 questions)

Prerequisites

Programme Guide; Modules 1–4

Introduction

Effective fault-finding identifies the underlying cause, corrects it once, verifies the repair and leaves a record that assists future work. Replacing components until a system operates again is costly, often fails to address the cause and destroys evidence. Many systems partners attend will have been installed by others. This module sets out a systematic and honest approach to diagnosis, repair and maintenance.

Learning outcomes

On completing this module, partners should be able to:

  1. Apply a structured diagnostic method;
  2. Select and use test instruments safely;
  3. Use alarms, logs and monitoring data as evidence;
  4. Diagnose common faults in PV arrays, inverters, batteries and AC circuits;
  5. Use voltage-drop measurements to locate excessive resistance;
  6. Assess an existing installation safely and fairly;
  7. Repair the root cause and verify the repair;
  8. Carry out preventive maintenance;
  9. Report findings accurately and objectively.

5.1 Diagnostic method

Key points

A complaint must be converted into a precise symptom before diagnosis begins.

Evidence is collected before anything is changed.

Possible causes are eliminated systematically until one remains.

Define the symptom. A complaint such as "the solar is not working well" must be established as a specific symptom, for example: "The inverter shuts down with a low-battery alarm at about 02:00 each night, since last month." The partner should establish what happens, when, how often, since when, and whether anything changed at that time.

Collect evidence. Alarm codes, event logs, settings and readings are recorded before any change is made. Restarting or resetting equipment may erase them.

Inspect safely. Signs of overheating, damage, water ingress, loose conductors and abnormal noise are noted, using safe isolation where equipment is opened (Module 2).

List and eliminate causes. Using knowledge of system operation, possible causes are listed and tests selected to eliminate as many as possible at each step. Useful techniques include comparison with a known good part of the system, comparison with baseline readings, and the half-split method: measuring at the midpoint of a circuit to determine in which half the fault lies. Faults should be reproduced only where this is safe.

Replacing the component that "usually fails" is not diagnosis. It adds cost, frequently leaves the cause in place and removes evidence.

5.2 Test instruments

Key points

Instruments must be appropriate, correctly rated and in good condition.

DC current measurement requires a DC-capable clamp meter.

Resistance and continuity are measured only on dead circuits.

Instrument

Measures

Precautions

Multimeter

DC and AC voltage; resistance; continuity

Correct CAT and voltage rating; leads in the correct sockets; resistance on dead circuits only

DC clamp meter

DC and AC current without disconnection

Must be DC-capable; zero before use; clamp a single conductor

Insulation resistance tester

Insulation between conductors and earth

Applies high test voltage; isolate the circuit, disconnect sensitive equipment, discharge afterwards

Earth tester

Earth electrode resistance

Follow the instrument's test-spike method

Infrared thermometer or thermal camera

Surface temperature

Reflective metal gives false low readings

Irradiance meter

Solar irradiance (W/m²)

Used to judge whether PV output is reasonable

Safe practice includes inspecting instruments and leads before use, selecting the function and range before connection, connecting the common lead first and removing it last, keeping fingers behind probe guards, and avoiding measurement in wet conditions.

5.3 Alarms, logs and monitoring

Key points

An alarm code is evidence and must be recorded with its conditions.

Codes are interpreted from the manual for the exact model and firmware.

Alarm codes differ between manufacturers and models. The partner should record the exact code with a photograph, note the conditions (time, load, battery state, weather, grid and generator status), consult the correct manual, carry out only approved checks, and escalate with the evidence if the fault is not resolved. Clearing codes without understanding them, altering settings experimentally and factory resets destroy evidence and may introduce new faults.

Monitoring data shows system behaviour in the partner's absence: daily PV yield compared with the season and previous weeks (a sudden fall suggests a fault; a gradual fall suggests soiling or ageing), overnight battery state of charge, load profile and event history. These are compared with the baseline readings recorded at commissioning.

5.4 PV array faults

Key points

Output must first be compared with what is reasonable for the conditions.

Identical strings in the same conditions should perform similarly; a fault confined to one string lies within that string.

Insulation faults often appear in morning dew or after rain.

Before a fault is suspected, output should be compared with the time of day, cloud, temperature, soiling and season, using an irradiance meter or a comparable nearby system where available, and with the system's history and baseline readings.

Where identical strings share orientation and conditions, a string that performs significantly worse than the others indicates a fault within that string, since the conditions, inverter and settings are common to all.

Symptom

Probable causes

Checks

Whole array low

Soiling, heat, cloud, settings, inverter power limiting

Conditions, cleanliness, settings, derating messages

One string low

Shading, soiling, damaged module, bypass diode, connector

Visual inspection; string Voc and current compared with other strings

One string zero

Open circuit: unmated connector, broken conductor, blown fuse, open isolator

Continuity and voltage along the string, with the circuit made safe

String Voc reduced by about one third of a module

Failed (short-circuited) bypass diode

Individual module Voc; thermal imaging

Insulation fault alarm, typically morning or after rain

Damaged insulation; water in a connector or junction box; cable abrasion

Insulation resistance per string; inspection of connectors and routes

Hot spots or burn marks

Cracked cells, shading, diode failure

Thermal imaging; warranty replacement where defective

Discoloured or melted connector

Contact resistance: mixed brands, poor crimp, water ingress

Replace with matched, correctly crimped connectors

5.5 Inverter faults

Key points

Many inverter alarms indicate that the inverter is correctly protecting itself from an external condition.

External causes should be eliminated before the inverter is suspected.

Inverters should not be opened without authorisation.

Fault

Typical cause

Checks

Overload

Load exceeds continuous rating, or motor starting surge

Loads at the time; surge rating (unit 5.7)

Over-temperature

Poor ventilation, blocked fans or filters, direct sun

Location, clearances, fans, dust

Grid fault

Grid voltage or frequency outside limits

Supply measurements; the inverter is correctly rejecting poor supply

Generator rejected

Unstable generator voltage or frequency under load

Generator condition and output; inverter generator settings

Battery communication fault

Cable, protocol setting or BMS status

Cable, settings, BMS

Low-battery shutdown

Discharged battery, voltage drop, incorrect cut-off, capacity loss

Unit 5.6

PV over-voltage

Excessive modules in series for low temperatures

String design (Module 3, unit 3.11)

Insulation fault

PV insulation damage

Unit 5.4

Where the inverter itself is faulty, the model, serial number, firmware version, fault codes, logs and photographs should be collected to support a warranty claim. Inverters retain stored charge and may lose warranty cover if opened without authorisation.

5.6 Battery faults

Key points

Reduced backup has several possible causes, of which battery degradation is only one.

Voltage drop under load reveals resistance in cables and connections.

BMS alarms identify which limit has been reached; the reason must be established.

Loss of voltage along a path

Where 25.6 V is present at the battery terminals but 0 V at the inverter's battery input, the voltage is being lost between them. The path is checked point by point: battery fuse or breaker, isolator, lugs, conductors and inverter terminals. The fault lies between the last point at which the voltage is present and the first at which it is absent. Components outside this path cannot be the cause.

Voltage drop under load

A high-resistance connection may show no voltage difference with no load, since V = I × R and no current produces no drop. Under load, the resistance becomes apparent.

Worked example. At an 80 A load, the battery terminals read 25.6 V and the inverter input 23.0 V.

  • Voltage lost: 25.6 − 23.0 = 2.6 V
  • Path resistance: 2.6 ÷ 80 = 0.0325 Ω
  • Power dissipated: 2.6 × 80 = 208 W, concentrated at the defective joint

The battery is maintaining its voltage; the inverter reports low battery because of losses in the path. The drop across each lug, fuse, breaker and conductor is measured to locate the fault, which must be corrected before any battery replacement is considered.

Reduced backup time

Since runtime equals usable energy divided by load, reduced backup results from increased load, reduced stored energy, losses, or changed settings.

Possible cause

Evidence

Increased load

New appliances; load readings during backup; monitoring history

Incomplete charging

SoC at start of night; PV yield; soiling or shading; charge settings

Changed settings

Cut-off voltage or SoC; charge limits

Connection losses

Voltage drop under load

Capacity loss

BMS state of health; cell voltage spread; alarm history; controlled capacity test

Raising charge voltages or lowering cut-off limits conceals the symptom and may damage the battery.

BMS alarms

Alarm

Meaning

Investigate

Cell over-voltage

A cell exceeded its limit during charging

Charge settings, cell imbalance, communication

Cell under-voltage

A cell fell below its limit

Over-discharge, cut-off setting, weak cell

Over-temperature

Battery too hot

Location, ventilation, current, cell condition

Over-current

Current exceeded the battery's limit

Inverter current settings, loads, parallel imbalance

Cell imbalance

Cells at differing voltages

Time at full charge for balancing; persistent imbalance may indicate a weak cell

In lead-acid banks, a single weak block limits the string. Block voltages should be measured under load; a block significantly lower than the others is defective. New blocks should not be mixed with aged blocks.

5.7 AC and load faults

Key points

A tripping protective device is operating correctly; the condition it is responding to must be found.

RCDs must never be bypassed, and breakers must never be upsized to stop tripping.

Motor starting is the most common cause of start-up trips.

Tripping pattern

Probable cause

Checks

After a period of operation

Overload

Circuit current; connected loads

Immediately on closing

Short circuit

Insulation resistance; cable and appliance damage

When a particular appliance starts

Faulty appliance or starting current

Operation with the appliance disconnected

With heating at the device or cable

Loose connection or undersized cable

Terminal condition and torque; conductor size (isolated)

Any change to protection is considered only after the cause is known, and the device must continue to protect the cable (Module 2, unit 2.9).

RCD tripping

An RCD trips when current leaks to earth. Common causes are moisture in outdoor accessories, junction boxes or connectors (hence tripping in rain); damaged insulation; appliances with leakage to their enclosures, such as water heaters; and incorrect neutral–earth arrangements. The faulty circuit is identified by isolating circuits in turn, then the appliances on it; insulation resistance is tested; and the fault is repaired and tested before re-energisation. An RCD that trips in rain is providing protection against electric shock. Bypassing it or replacing it with a device that does not detect leakage removes that protection.

Motor starting

Where an inverter supplies normal loads but trips when a pump or compressor starts, the following are checked: the motor's starting current or power (typically 3 to 7 times running); the inverter's surge rating and duration; battery voltage during starting; and voltage drop in battery and motor cables. Remedies, such as a soft starter or variable-speed drive, larger conductors, battery replacement or a larger inverter, are design decisions for EcoStride.

Supply quality

Grid voltage outside the inverter's limits causes the grid to be rejected, and should be measured at different times and reported. Generators with unstable speed under load produce unstable frequency, which inverters commonly reject; servicing or adjustment of inverter settings within the manufacturer's limits may be required. On three-phase sites, imbalance between phases can overload one phase or inverter.

5.8 Assessment of existing installations

Key points

No assumption is made about an installation the partner did not install. All conductors are treated as live until proved dead.

Findings are classified as safety hazards, performance problems or recommendations.

Findings are reported accurately, without exaggeration or omission.

Many systems partners attend were installed without adequate design, protection or earthing. Wiring may not match any drawing; labels may be absent or wrong; protective devices may be AC-only on DC circuits, undersized or bypassed; earthing may be missing; and batteries may be damaged, mixed or overheating.

Before any work, the partner looks for immediate hazards: exposed live parts, burn marks, swollen batteries, melted insulation, bypassed protection and unsafe generator connections. Where a hazard is found, the partner makes the situation safe if it can be done safely, informs the customer clearly and reports to EcoStride immediately.

The assessment then proceeds as follows:

  1. establish the customer's concerns and the history of the system;
  2. record all components, ratings, labels and layout with photographs;
  3. review alarm history, settings and monitoring data;
  4. measure string voltages and currents, battery voltage at rest and under load, voltage drop, AC voltages, and insulation and earth resistance where safe;
  5. compare the installation with the practice described in Modules 2 to 4;
  6. classify the findings.

Category

Definition

Example

Safety hazard

Could cause injury or fire; requires immediate action

Missing earth; AC breaker on a PV string; swollen battery

Performance problem

System does not deliver its intended performance

Shaded array; undersized battery cables; incorrect settings

Recommendation

An improvement rather than a fault

Monitoring; load efficiency

Findings must reflect the evidence. Problems must not be exaggerated to generate work or omitted to avoid difficult conversations. Previous installers should not be criticised; the problem and its significance should be described. Repairs and prices are not promised on site; EcoStride follows up with solutions. Measured facts are distinguished from opinions.

5.9 Repair and verification

Key points

The root cause, not only the symptom, must be corrected.

A fault that produced heat may have caused further damage.

Repairs are verified under load.

Before repair, the circuit is isolated and proved dead (Module 2, unit 2.6). Replacement parts must match the original specification or the approved design. For warranty repairs, serial numbers, fault codes, logs, photographs and readings are collected first, and sealed equipment is not opened without authorisation from the manufacturer or EcoStride.

After a repair, such as tightening a loose battery terminal, the partner:

  1. inspects related connections, which may have been installed in the same way;
  2. examines the repaired joint and adjacent components for heat damage, replacing rather than re-tightening where necessary;
  3. tests under the load conditions that produced the fault, including voltage drop across the joint;
  4. checks for abnormal temperature after operation under load;
  5. records the fault, cause, action and post-repair results.

5.10 Preventive maintenance

Key points

Preventive maintenance identifies deterioration before it causes failure.

A maintenance visit is a complete inspection, not only module cleaning.

Readings are compared with baseline values to detect gradual change.

Area

Checks

Safety

Safe access; isolators operational; labels present and legible

Array

Soiling; cracked glass, burn marks or discolouration; new shading

Structure and roof

Fixings secure; no corrosion; penetrations sealed; no internal leaks

Cables and connectors

Supports intact; no abrasion or rodent damage; no discolouration

Inverter

Ventilation clear; fans and filters clean; alarm and event history

Battery

Temperature, SoC and SoH from BMS; cell balance; terminals clean and tight; no swelling or leakage

Protection and earthing

SPD indicators; RCD test; earth connections secure

Performance

Readings compared with baseline and expected output

Customer

Concerns, patterns of use and changes in load

Modules are cleaned in the early morning or evening, when they are cooler and producing less current, since cold water on hot glass may cause cracking. Clean water and a soft brush or sponge are used; hard water, detergents and abrasives damage the anti-reflective coating. Modules must not be walked or knelt on, and all work-at-height controls apply (Module 2, unit 2.4). Cleaning may be required more frequently during the harmattan.

Connections loosen over time through thermal cycling. A sample of key terminals should be checked with a torque tool and a thermal check made under load.

5.11 Reporting

Key points

Service reports must be accurate, specific and complete.

Measured facts are distinguished from opinion.

Reports are submitted promptly in the format EcoStride provides.

Service reports are submitted by WhatsApp in the standard format provided by EcoStride. Each report should state:

  1. the fault reported and the symptom confirmed;
  2. observations, measurements and alarm codes, with photographs;
  3. the cause, based on the evidence, or a statement that it is not yet established;
  4. the action taken and parts used;
  5. results after repair, demonstrating operation under load;
  6. any outstanding work and the reason;
  7. recommendations, with safety hazards first.

Fact

Opinion (unless tested)

"Voltage drop between battery and inverter is 2.6 V at 80 A."

"The cables are bad."

"String 2 current is 4.1 A; strings 1 and 3 are 11.8 A."

"String 2 is dead."

"BMS state of health is 71%."

"The battery is finished."

A fault must never be reported as corrected when it is not, and findings must not be exaggerated or concealed. Errors discovered from earlier jobs are reported (Module 1, unit 1.10). Safety hazards are reported immediately, not at the end of the visit.

Case studies

The following cases are based on situations commonly encountered on Nigerian sites. Names and places are illustrative.

Case 1: Battery wrongly condemned. A school in Abeokuta was advised that its battery bank needed replacement. A partner measured 51.8 V at the battery terminals and 46.9 V at the inverter under load. A corroded lug on the main negative conductor was dropping almost 5 V; replacing it restored normal backup time. Principle: unit 5.6.

Case 2: Bypassed RCD. A restaurant's RCD tripped whenever it rained, and a previous electrician had bypassed it. A partner found water in a roof junction box with an unsealed cable entry. After sealing, drying and insulation testing, the RCD was reinstated and did not trip again. Principle: unit 5.7.

Case 3: Evidence-based assessment. A customer in Asaba had been told she needed a new inverter. The partner found the inverter serviceable and the array shaded by a newly installed water tank, and reported this with photographs and string readings, recommending relocation of three modules. Principle: units 5.4 and 5.8.

Relationship to performance rating

Rating measure

Relevant units

Callbacks

5.1, 5.9

Reporting

5.3, 5.8, 5.11

Quality of workmanship

5.9, 5.10

Customer rating

5.8

Safety-critical conduct

5.7: bypassing or disabling a protective device is treated as a serious breach

Practical activities

  1. Practise converting a vague complaint into a precise symptom, using the questions in unit 5.1.
  2. On an operating system, measure battery voltage at the terminals and at the inverter under load, and calculate the voltage drop and path resistance.
  3. Measure and compare the currents of identical strings with a DC clamp meter.
  4. Select three alarm codes from an inverter manual and record their meaning and the checks required.
  5. Assess an existing installation using the procedure in unit 5.8 and classify the findings.
  6. Write a service report for one of the case studies above, following unit 5.11.

Glossary

Term

Definition

Baseline readings

Measurements recorded at commissioning for later comparison

Capacity test

A controlled discharge to measure a battery's deliverable energy

Cell imbalance

Differences in voltage or state of charge between cells

DC clamp meter

An instrument measuring DC current by clamping around a single conductor

Half-split method

Testing at the midpoint of a circuit to halve the area of search

Insulation fault

An inverter indication that PV insulation resistance is below its limit

Preventive maintenance

Planned inspection and servicing to detect deterioration before failure

Root cause

The underlying reason for a fault

Safety hazard

A finding that could cause injury or fire and requires immediate action

Soft starter / VSD

Devices that reduce motor starting current

Symptom

A specific, observable description of a fault and its occurrence

Voltage drop

Voltage lost along a conductor or connection due to resistance

Warranty claim

A request to a manufacturer to repair or replace defective equipment, supported by evidence

Rating
0 0

There are no comments for now.

1. Your clamp meter reads 0 A on a PV cable while the inverter shows the string producing power. What is the most likely explanation?
3. An inverter shows an insulation fault alarm most mornings, which clears by mid-morning. What is the most likely cause?