Skip to Content

Module 3: Electrical Fundamentals, Site Assessment & System Design

Module 3: Electrical Fundamentals, Site Assessment & System Design

24 sept. 2026

Module information


Audience

Applicants to the EcoStride Installation Partner Programme

Study time

About 4 hours

Units

13

Assessment

Part 1, Segment 3 (10 questions)

Prerequisites

Programme Guide; Modules 1 and 2

Materials

Basic calculator

Introduction

Correct design and installation depend on understanding how electrical systems behave. This module covers the electrical principles, component characteristics, site assessment and sizing methods required to specify a safe and suitable solar and battery system. Each worked example should be reproduced with a calculator.

Learning outcomes

On completing this module, partners should be able to:

  1. Apply the relationships between voltage, current, resistance, power and energy;
  2. Distinguish between power (kW) and energy (kWh);
  3. Calculate voltage and current for series and parallel connections;
  4. Interpret a PV module datasheet and the effects of temperature, shading and soiling;
  5. Describe the function and key ratings of inverters, charge controllers and batteries;
  6. Identify the main system types;
  7. Conduct a site assessment and load analysis;
  8. Size an inverter, battery and PV array for a simple system;
  9. Verify that a string configuration is within an inverter's voltage limits;
  10. Explain cable selection and calculate voltage drop;
  11. Verify equipment compatibility.

3.1 Electrical quantities

Key points

Voltage drives current; resistance opposes it.

V = I × R and P = V × I are the basis of most calculations in this module.

Resistance in a conductor or connection converts power into heat: P = I² × R.

Quantity

Symbol

Unit

Voltage

V

volt (V)

Current

I

ampere (A)

Resistance

R

ohm (Ω)

Power

P

watt (W)

Example 1. A 230 V appliance draws 8 A. P = 230 × 8 = 1,840 W.

Example 2. A 2,000 W kettle operates at 230 V. I = 2,000 ÷ 230 = 8.7 A.

At 230 V, each ampere corresponds to approximately 230 W. Results should be checked against this order of magnitude.

Example 3: heat at a poor connection. A battery lug with a resistance of 0.05 Ω carries 40 A. Heat produced = 40² × 0.05 = 80 W, concentrated in a single joint, with a voltage loss of 40 × 0.05 = 2 V. Because heat is proportional to the square of the current, doubling the current produces four times the heat. This is the mechanism by which loose terminals, poor crimps and undersized conductors cause fires.

3.2 Energy: kW and kWh

Key points

Power (kW) is a rate; energy (kWh) is a quantity.

Inverters are rated in kW; batteries and consumption are measured in kWh.

Example. A 0.75 kW compressor runs for 6 hours: E = 0.75 × 6 = 4.5 kWh.

Confusion between kW and kWh is a common cause of mis-sized systems and customer misunderstanding. A request for "a 5 kW system" may refer to an inverter, a battery or an array, which are different quantities.

Battery capacity stated in ampere-hours is converted to energy as follows:

A 12 V, 100 Ah battery stores 12 × 100 ÷ 1,000 = 1.2 kWh.

3.3 AC and DC; single-phase and three-phase

Key points

PV modules and batteries produce DC; buildings use AC. The inverter converts between them.

Motors and similar loads require more apparent power (kVA) than real power (kW).

Direct current (DC) flows in one direction and has positive and negative polarity. Alternating current (AC) reverses direction periodically; the Nigerian supply operates at 50 Hz.

Single-phase supplies have one line conductor and a neutral at approximately 230 V (240 V in older documentation) and serve most homes and small premises. Three-phase supplies have three line conductors, each at 230 V to neutral and approximately 400 V (415 V) between lines, and serve larger premises and loads. Three-phase loads should be balanced across the phases, and three-phase sites require a three-phase inverter or single-phase inverters designed to operate together.

For loads such as motors, pumps and compressors, current is not fully in phase with voltage. Such loads draw apparent power (kVA) greater than the real power (kW) they consume:

A 5 kVA inverter supplying loads with a power factor of 0.8 can deliver 5 × 0.8 = 4 kW.

3.4 Series and parallel connections

Key points

In series, voltages add and current is common.

In parallel, currents add and voltage is common.

In series, the same current passes through each device in turn and each contributes its voltage. In parallel, each device is connected across the same two conductors and their currents combine.

PV modules (three identical modules, each Vmp 40 V, Imp 11 A):

Connection

Voltage

Current

Power

Series

120 V

11 A

1,320 W

Parallel

40 V

33 A

1,320 W

Series connection is generally preferred because lower current reduces conductor size and I²R losses, subject to the inverter's voltage limits (unit 3.11).

Batteries (four identical 12 V, 200 Ah units):

Connection

Voltage

Capacity

Energy

4 in series

48 V

200 Ah

9.6 kWh

4 in parallel

12 V

800 Ah

9.6 kWh

2 series × 2 parallel

24 V

400 Ah

9.6 kWh

Batteries connected together must be of the same type, capacity, age and condition.

3.5 PV modules

Key points

Module output depends on irradiance, temperature, shading and soiling.

Increasing temperature reduces voltage and power; low temperature increases voltage.

In a series string, shading of one module can reduce the output of the whole string.

Irradiance and peak sun hours

Irradiance is the power of sunlight per unit area, in W/m²; full midday sun is approximately 1,000 W/m². Peak sun hours (PSH) express a day's total solar energy as the equivalent number of hours at 1,000 W/m². Typical values in Nigeria range from about 4 to 6.5 depending on location and season.

Datasheet parameters

Module ratings are stated at Standard Test Conditions (STC): 1,000 W/m² irradiance and 25 °C cell temperature.

Parameter

Definition

Example (550 W module)

Pmax

Maximum power at STC

550 W

Vmp

Voltage at maximum power

41.9 V

Imp

Current at maximum power

13.13 A

Voc

Open-circuit voltage

49.6 V

Isc

Short-circuit current

14.0 A

Temperature coefficient of Pmax

Change in power per °C

−0.35 %/°C

Temperature coefficient of Voc

Change in voltage per °C

−0.27 %/°C

Temperature effects

On Nigerian roofs, cell temperatures of 60–70 °C are common in full sun.

Example: high temperature. At 65 °C (40 °C above STC), power falls by 40 × 0.35% = 14%, giving approximately 550 × 0.86 = 473 W.

Example: low temperature. At 15 °C (10 °C below STC), Voc rises by 10 × 0.27% = 2.7%, to approximately 49.6 × 1.027 = 50.9 V.

High temperatures determine the minimum operating voltage of a string; low temperatures determine the maximum voltage the inverter must withstand (unit 3.11).

Shading, soiling and ageing

In a series string, all modules carry the same current, so a shaded module limits the string. Bypass diodes, typically three per module, allow current to pass around shaded cell groups; they reduce the loss and prevent overheating, but the output of the bypassed section is lost. Harmattan dust and bird droppings reduce output until modules are cleaned. Modules also degrade gradually, typically by about 0.4–0.7% per year. In Nigeria, modules generally face south at a tilt of at least 10–15° to allow rain to clean them.

3.6 Inverters and charge controllers

Key points

Continuous rating, surge rating, battery voltage and PV input limits must all suit the design.

MPPT controllers extract significantly more energy than PWM controllers.

Inverter type

Battery

Grid connection

Behaviour during grid outage

Off-grid

Yes

None, or charging only

Supplies loads from battery and PV

Grid-tied

No

Yes

Shuts down

Hybrid

Yes

Yes

Supplies loads from battery and PV; usually accepts a generator

Most EcoStride systems are hybrid, reflecting the need for backup during grid outages.

Specification

Design consideration

Rated output (kW/kVA)

Must cover the simultaneous load

Surge rating

Must cover motor starting

Battery voltage

Must match the battery

MPPT voltage range

String operating voltage must remain within it

Maximum PV input voltage

String maximum Voc must remain below it; exceeding it causes damage

Maximum PV input current

String current must not exceed it

Maximum charge current

Must not exceed the battery's limit

Transfer time

Relevant to sensitive loads

Efficiency

Typically 90–97%; losses become heat

Operating temperature

Output is reduced (derated) at high temperature

A PWM charge controller connects the modules almost directly to the battery, holding them at battery voltage, well below their maximum power point. An MPPT controller converts the module voltage to the battery voltage while keeping the modules at their maximum power point.

Example. A module with Vmp 18 V and Imp 5.5 A (about 99 W) charges a 12 V battery at 13.5 V. With PWM, output is approximately 13.5 × 5.5 = 74 W. With MPPT, output is approximately 96 W after conversion losses.

3.7 Batteries

Key points

Usable energy is less than rated energy and is limited by depth of discharge.

Lithium iron phosphate (LFP) batteries provide greater usable energy and cycle life than lead-acid, and always require a BMS.

High temperature shortens battery life.


Flooded lead-acid

Sealed lead-acid (AGM, gel)

Lithium iron phosphate (LFP)

Recommended depth of discharge

About 50%

About 50%

About 80–90% or more

Typical cycle life

Several hundred to about 1,200

Several hundred to about 1,000

About 3,000–6,000 or more

Round-trip efficiency

About 80–85%

About 80–85%

About 95%

Maintenance

Water topping; ventilation

Low

Very low

BMS required

No

No

Yes

Cycle life depends strongly on depth of discharge and temperature; the manufacturer's data should be consulted. Lead-acid cells are 2 V (six per 12 V block). LFP cells are 3.2 V; a 16-cell battery has a nominal voltage of 51.2 V and is commonly described as "48 V".

Example. A 51.2 V, 100 Ah LFP battery at 90% depth of discharge supplies a 500 W load through an inverter of 92% efficiency.

  1. Rated energy: 51.2 × 100 ÷ 1,000 = 5.12 kWh
  2. Usable energy: 5.12 × 0.90 = 4.61 kWh
  3. Delivered AC energy: 4.61 × 0.92 = 4.24 kWh
  4. Runtime: 4.24 ÷ 0.5 = approximately 8.5 hours

The C-rate relates current to capacity: for a 100 Ah battery, 0.5C is 50 A. Maximum charge and discharge currents are stated on the datasheet. High temperature accelerates ageing; as a guide, a lead-acid battery operated at 35 °C rather than 25 °C may lose about half its service life.

The battery management system (BMS) of a lithium battery monitors cell voltages and temperatures, disconnects the battery outside safe limits, limits current, balances cells, estimates state of charge (SoC) and state of health (SoH), and communicates with the inverter.

3.8 System types

System type

Description

Typical application

Solar home system

Small kit with module, battery and controller

Basic loads in off-grid homes

Off-grid

PV and battery supply all loads, often with generator backup

Sites without grid connection

Grid-tied

PV operates alongside the grid without storage

Reducing daytime consumption where supply is reliable

Hybrid

PV, battery, grid and usually generator, managed by a hybrid inverter

Premises with unreliable grid supply

Mini-grid

A generating system supplying multiple customers through a local network; regulated by NERC

Rural communities and markets

In a DC-coupled system, the PV array connects to the inverter's MPPT input and charges the battery on the DC side; this is the usual hybrid arrangement. In an AC-coupled system, a separate grid-tied PV inverter supplies AC, and a battery inverter charges the battery from AC.

3.9 Site assessment

Key points

A design is only as reliable as the information on which it is based.

Information should be measured and observed, not assumed.

Defects in the existing installation must be recorded and reported.

Area

Information required

Purpose

Customer requirements

Loads required during outages, required duration, expected savings

Defines the design objective

Supply

Grid availability and quality, generator size and use, single- or three-phase

Determines system type and source connection

Loads

Appliances, ratings, hours of use, simultaneous operation (unit 3.10)

Sizes the inverter and battery

Roof or ground area

Material, condition, structure, pitch, orientation, available area

Determines mounting method and array size

Shading

Trees, tanks, walls, poles and adjacent buildings at different times of day

Determines array location and expected yield

Equipment location

Dry, cool, ventilated, secure and accessible space

Protects equipment life and safety

Cable routes

Routes and lengths between array, battery, inverter and distribution board

Determines cable sizes and voltage drop

Existing installation

Condition of wiring, distribution boards, protective devices and earthing

Identifies hazards to be resolved

Access

Roof access, fragile surfaces, security

Informs work-at-height planning

In Nigeria the sun passes close to overhead, predominantly to the south, and is low in the east and west in the early morning and late afternoon. Obstructions above the array's horizon on the southern, eastern or western side will shade it at some time of day and should be recorded with photographs.

Many existing installations have missing earths, undersized cables, overloaded distribution boards or signs of overheating. Connecting a new system to an unsafe installation increases the hazard. Such defects must be recorded and reported as part of the assessment.

3.10 Load analysis

Key points

A load analysis records each appliance's power, hours of use and starting surge.

Electricity bills show total energy only, not timing, simultaneity or surge.

Improving load efficiency reduces the size and cost of every component.

A bill of 300 kWh per month indicates average consumption of about 10 kWh per day. It does not show when energy is used, which loads operate together, which have starting surges, or which are essential during outages. Where supply is unreliable, it also reflects only the energy received, not the energy required.

Load table

The following example is a small shop open from 09:00 to 17:00.

Appliance

Qty

Power each

Total power

Hours per day

Energy per day

LED lights

10

10 W

100 W

8

0.80 kWh

Ceiling fans

3

75 W

225 W

8

1.80 kWh

Laptop and POS

2

65 W

130 W

8

1.04 kWh

Drinks chiller (starting surge 750 W)

1

150 W

150 W

12 (50% duty over 24 h)

1.80 kWh

Television

1

100 W

100 W

6

0.60 kWh

Total



705 W


6.04 kWh

Continuous power is the total of loads that may operate simultaneously: 705 W. Surge power is the continuous load with the largest motor at its starting power instead of its running power:

Motors, compressors and pumps typically draw 3 to 7 times their running power when starting. Where two motors may start simultaneously, both are included.

The customer should identify essential loads to be supplied during outages; these are normally connected to a separate backed-up distribution board and clearly labelled. Where appropriate, efficiency measures such as LED lighting, inverter-type appliances and scheduling heavy loads during daylight should be recommended to EcoStride.

3.11 System sizing

Key points

The inverter is sized for power (kW), the battery for energy (kWh) and the array for daily energy.

Allowances must be made for losses, depth of discharge and design margin.

Each string must satisfy two voltage checks: hot operating voltage and cold open-circuit voltage.

This worked example continues from unit 3.10: continuous load 705 W, surge 1,305 W, daily energy 6.04 kWh.

Step 1: Inverter

  • Continuous rating with a 25% margin: 705 × 1.25 ≈ 0.9 kW
  • Surge capability: at least 1.3 kW

A standard size providing capacity for future loads, such as a 3 kVA, 48 V hybrid inverter, would normally be selected.

Step 2: Battery

The customer requires the chiller to operate overnight and normal loads to run for 3 hours during a cloudy grid outage.

  • Overnight chiller: 150 W × 16 h × 0.5 duty = 1.2 kWh
  • Daytime loads without chiller: 555 W × 3 h = 1.67 kWh
  • Energy required at the loads: 2.87 kWh
  • Allowing for inverter efficiency (92%): 2.87 ÷ 0.92 = 3.12 kWh usable
  • Allowing for depth of discharge (90%): 3.12 ÷ 0.90 = 3.47 kWh rated

A 51.2 V, 100 Ah LFP battery (5.12 kWh) meets the requirement with margin for ageing and growth.

Step 3: PV array

A performance factor of approximately 0.75 allows for temperature, soiling, cable and battery losses.

With 5 peak sun hours: 6.04 ÷ (5 × 0.75) ≈ 1.61 kWp, requiring at least three 550 W modules.

Step 4: String voltage

The inverter has an MPPT range of 120–450 V and a maximum PV input of 500 V. Using the module in unit 3.5, hot Vmp is approximately 41.9 × 0.86 = 36.0 V and cold Voc approximately 50.9 V per module.

Modules in series

Hot Vmp

Cold Voc

Result

3

108 V

153 V

Fails: below MPPT minimum

4

144 V

204 V

Passes

9

324 V

458 V

Passes

10

360 V

509 V

Fails: exceeds maximum input voltage

The design therefore uses 4 modules (2.2 kWp). The voltage check increased the array size above the energy requirement, and the 10-module case shows that open-circuit voltage at low temperature, not operating voltage, sets the maximum string length. String current (Isc 14.0 A) must also be within the inverter's input current limit.

3.12 Cables and voltage drop

Key points

A cable must carry its current without overheating, limit voltage drop and be protected by its overcurrent device.

Ambient temperature, grouping and installation method reduce current-carrying capacity.

Low-voltage, high-current circuits such as battery cables require the largest conductors.

A cable's rated current-carrying capacity applies to reference conditions. High ambient temperatures (air beneath a roof sheet can greatly exceed 40 °C), grouping with other cables, and enclosure in conduit or insulation reduce it, in combination often by a third or more. Correction factors are given in manufacturers' tables and the applicable standards.

For DC and single-phase circuits, where current flows out and back:

where L is the one-way length (m), I the current (A), A the conductor cross-section (mm²) and ρ the resistivity of copper, approximately 0.0175 Ω·mm²/m at 20 °C.

Example 1: battery cable (48 V, 100 A, 3 m one way).

Conductor

Resistance

Voltage drop

Power loss

10 mm²

0.0105 Ω

1.05 V (2.2%)

105 W

25 mm²

0.0042 Ω

0.42 V (0.9%)

42 W

Undersized battery cables waste energy as heat and reduce the voltage at the inverter, which can cause false low-battery shutdowns under load.

Example 2: PV string cable (approximately 168 V, 13.13 A, 30 m one way).

Conductor

Voltage drop

Percentage

4 mm²

3.4 V

2.1%

6 mm²

2.3 V

1.4%

Designers commonly limit DC voltage drop to about 1–3%. The overcurrent device must not exceed the derated capacity of the cable (Module 2, unit 2.9), and the conductor must suit the equipment terminals.

3.13 Equipment compatibility

Key points

A nominal voltage label is not a specification.

Voltage ranges, current limits, chemistry, communication and manufacturer approval must all be confirmed.

A 16-cell LFP battery is 51.2 V nominal and operates between approximately 44.8 V and 57.6 V. A 48 V lead-acid bank charges at approximately 57–58 V and floats at approximately 54 V. Equipment described as "48 V" may therefore not be compatible.

Before equipment is approved, the following must be confirmed:

Interface

Checks

Battery and inverter

Overlapping voltage ranges; charge and discharge current limits; correct chemistry profile; BMS communication interface and protocol; manufacturers' compatibility approval

Array and inverter

Hot and cold string voltage checks; string current within MPPT input limit; array power within PV input rating

Protection

DC rating at maximum circuit voltage and correct polarity; adequate breaking capacity; RCD type as specified by the inverter manufacturer

Equipment is not approved until every item has been confirmed.

Case studies

The following cases are based on situations commonly encountered on Nigerian sites. Names and places are illustrative.

Case 1: kVA and kWh confused. A customer in Owerri was told he had "a 5 kVA system" and expected it to supply his home overnight. The system had a 5 kVA inverter but a 2.4 kWh battery, which was exhausted by midnight. Principle: units 3.2 and 3.7.

Case 2: Motor starting. A hotel in Jos operated a 3 kW borehole pump from a 5 kVA inverter. The pump ran satisfactorily but tripped the inverter at every start, requiring approximately 12 kW momentarily. A soft starter resolved the problem. Principle: unit 3.10.

Case 3: Cold-morning overvoltage. Twelve modules with a datasheet Voc of 41 V (492 V in total) were connected to an inverter rated for 500 V maximum input. On a cold harmattan morning the string voltage exceeded 500 V and the inverter input was damaged. Principle: unit 3.11.

Relationship to performance rating

Rating measure

Relevant units

Callbacks

3.10, 3.11, 3.13

Quality of workmanship

3.12, 3.13

Customer rating

3.2, 3.7 (accurate expectations of system capacity)

Reporting

3.9

Practical activities

  1. Prepare a load table for a home or small business and calculate continuous power, surge power and daily energy.
  2. From a module datasheet, record Pmax, Vmp, Imp, Voc, Isc and the temperature coefficients, and calculate the output at 65 °C.
  3. Using the same module and any hybrid inverter datasheet, determine the minimum and maximum number of modules per string.
  4. Calculate the rated and usable energy of an installed battery and its runtime at 400 W.
  5. Measure a cable route on site and calculate the voltage drop for two conductor sizes.
  6. Record all potential sources of shading at a building.

Formulas

Quantity

Formula

Ohm's law

V = I × R

Power

P = V × I

Resistive heating

P = I² × R

Energy

E (kWh) = P (kW) × t (h)

Battery energy

E (kWh) = V × Ah ÷ 1,000

Usable battery energy

Rated energy × depth of discharge

Real power

kW = kVA × power factor

Surge power

Other loads + largest starting load

Array size

Daily energy ÷ (PSH × 0.75)

Temperature correction

Value × (1 + coefficient × temperature difference)

Voltage drop (DC or single-phase)

2 × L × I × 0.0175 ÷ A

Glossary

Term

Definition

Apparent power (kVA)

The product of voltage and current, including the effect of power factor

BMS

Battery management system; monitors and protects a lithium battery

Bypass diode

A diode allowing current to pass around a shaded group of cells

C-rate

Charge or discharge current relative to battery capacity

Continuous power

The total power of loads that may operate simultaneously

Depth of discharge (DoD)

The proportion of battery capacity used before recharging

Derating

Reduction of a rating to account for operating conditions

Irradiance

Solar power per unit area, in W/m²

MPPT

Maximum power point tracking

Peak sun hours (PSH)

Daily solar energy expressed as hours at 1,000 W/m²

Power factor

The ratio of real power (kW) to apparent power (kVA)

State of charge (SoC)

Stored energy as a percentage of capacity

State of health (SoH)

Remaining capacity as a percentage of original capacity

STC

Standard Test Conditions: 1,000 W/m² and 25 °C cell temperature

Surge power

Short-duration power required to start a motor

Temperature coefficient

Change in a parameter per °C of temperature change

Vmp, Imp, Voc, Isc

Voltage and current at maximum power; open-circuit voltage; short-circuit current

Voltage drop

Voltage lost along a conductor due to its resistance

Rating
0 0

There are no comments for now.

1. You are estimating the output of a 400 W module with a Pmax temperature coefficient of −0.4 %/°C. What output should you expect in full sun with cells at 55 °C?
3. You connect two identical 12 V, 150 Ah batteries in parallel. What are the resulting voltage, capacity and energy?
4. You find a connection with a resistance of 0.02 Ω carrying 60 A. How much heat is produced at the connection?