Skip to Content

Module 4: Installation, Configuration & Commissioning

Module 4: Installation, Configuration & Commissioning

24 sept. 2026

Module information


Audience

Applicants to the EcoStride Installation Partner Programme

Study time

About 2.5 hours

Units

11

Assessment

Part 1, Segment 4 (10 questions)

Prerequisites

Programme Guide; Modules 1–3

Introduction

A correct design will fail if it is poorly installed. Many faults found on solar installations in Nigeria result from workmanship shortcuts: fixings that miss the structure, cables abraded by sharp edges, mismatched connectors and incorrect settings. This module sets out the standards of workmanship, configuration, testing and commissioning required of Installation Partners, and the reasons for them.

Learning outcomes

On completing this module, partners should be able to:

  1. Prepare for an installation so that work is right first time;
  2. Explain how mounting systems resist wind load and maintain weathertightness;
  3. Route, terminate and label DC cables to a professional standard;
  4. Select suitable locations for inverters and batteries, and connect parallel batteries correctly;
  5. Connect AC supplies, including generators, without backfeed or incorrect earthing;
  6. Install effective earthing and surge protection;
  7. Configure equipment from approved information;
  8. Inspect and test a system before energisation and interpret the results;
  9. Commission a system by testing each operating mode;
  10. Complete handover with accurate records and an informed customer;
  11. Recognise and avoid common workmanship defects.

4.1 Preparation

Key points

Many installation defects can be prevented before arriving on site.

Delivered equipment must be checked against the design for conformity, authenticity and damage.

Before travelling, the partner should study the approved design until it is fully understood, including equipment, string configuration, cable sizes, protection and equipment locations. Queries should be raised with EcoStride before the job. Tools and PPE should be checked (Module 2, unit 2.3) and roof work planned for suitable weather.

On delivery, each item should be checked against the design for model, rating and quantity, and inspected for damage such as cracked glass, dented battery casings or broken connectors. Indicators of counterfeit or non-conforming products include poor labelling, missing ratings, conductors thinner than marked and unusually light protective devices. Any discrepancy must be reported to EcoStride with photographs before installation.

Work should be sequenced so that circuits remain isolated until testing is complete: structure and modules; cabling with all circuits isolated; inverter and battery; protection and earthing; inspection and testing; energisation.

4.2 Mounting structures and roofs

Key points

Wind uplift must be transferred through every fixing into the roof structure.

Every roof penetration is a potential leak and must be correctly sealed.

Module clamping zones and mounting-system instructions must be followed.

Wind flowing over and under a module creates an upward force that can exceed the module's weight. This load passes through clamps and rails to the fixings. A fixing that engages only the roof sheet may tear out, transferring its load to adjacent fixings, which may then fail progressively.

Roof type

Mounting approach

Precautions

Long-span metal sheet

Brackets fixed through the sheet into purlins or rafters

Locate supports; seal each penetration; avoid denting the sheet

Stone-coated steel tile

Tile hooks or brackets fixed to battens or rafters

Avoid damaging tiles; restore the weather seal

Concrete flat roof

Frames anchored to the slab, or ballasted where designed

Seal any membrane penetration; maintain drainage

Asbestos-cement sheet

No drilling, cutting or access without specialist controls

Asbestos dust causes fatal disease; sheets are fragile

Ground mount

Frames on concrete footings

Footings designed for wind load; protection from people, animals and vehicles

A fixing that misses its support must be removed, relocated into the structure and the unused hole sealed by an approved method. Penetrations must be sealed with the washers and outdoor-rated sealant specified by the mounting system.

Modules must be clamped only within the manufacturer's permitted zones, and clamps and bolts tightened to the specified torque. The specified spacing between modules and rails allows for thermal expansion and ventilation. Aluminium must not be placed in direct contact with copper or plain steel, as galvanic corrosion results; the mounting system's matched fasteners should be used. Rails and frames must be bonded to earth by the method the mounting system specifies.

4.3 DC wiring, connectors and polarity

Key points

PV cable must be adequately supported and protected from abrasion.

Connector pairs must be of the same manufacturer and type, and crimped with the correct tool.

Polarity must be verified before every connection.

PV cable is double-insulated, UV-resistant and rated for high DC voltages; general building wire is not suitable. Cables move continually under wind and thermal cycling, and abrasion against sharp edges can penetrate insulation within months, causing shock, earth-fault or fire hazards. Cables must therefore be:

  • fixed to the structure at short intervals with UV-resistant clips or ties;
  • kept clear of the roof surface;
  • protected at edges and entry points with grommets, conduit or glands;
  • run with positive and negative conductors together to minimise loop area;
  • formed into a drip loop before entering a building or enclosure;
  • labelled at each end.

PV connectors from different manufacturers may appear to mate but differ in dimensions, materials and seals. The resulting contact resistance produces heat (P = I² × R), which can melt the connector and cause fire, while a poor seal admits water. Both halves of a connection must be from the same manufacturer and of the same type. Conductors must be stripped to the specified length, crimped with the tool and die designed for the connector, pull-tested, and sealed by tightening the rear nut.

A multimeter indicates the voltage of the red probe relative to the black probe. With red on the conductor marked positive, a positive reading confirms correct polarity; a negative reading indicates reversed or mislabelled conductors. The circuit must remain disconnected until the fault is traced and corrected. Reversed battery polarity can destroy an inverter's input stage instantly.

String fuses are required where three or more strings are connected in parallel, to protect a faulted string from the combined current of the others. DC isolators must be rated for the maximum string voltage and current.

4.4 Inverter and battery installation

Key points

Inverters and batteries require locations that are dry, cool, ventilated, accessible and secure.

Parallel batteries must be connected so that current is shared equally.

Battery protection must be located close to the battery, and all terminals torqued to specification.

Inverter losses are dissipated as heat: a 5 kW inverter at 95% efficiency produces about 250 W. Elevated temperatures shorten the life of electronics and batteries and cause inverters to reduce output. A suitable location:

  • provides the manufacturer's minimum clearances for ventilation;
  • is shaded and cool, and is not a closed cupboard or unventilated room;
  • is dry and away from bathrooms, kitchens, water tanks and roof leaks;
  • is away from fuel, gas cylinders and other combustible materials;
  • allows safe operation and maintenance, with isolators within reach;
  • is secure against theft, tampering and access by children;
  • has a wall or floor capable of bearing the load.

Where a customer proposes an unsuitable location, the reasons should be explained and a suitable alternative agreed.

Parallel batteries

Current divides between parallel batteries in inverse proportion to the resistance of each path. If the inverter is connected to one end of the bank only, the nearest battery carries more current, cycles harder and ages sooner. Balanced current sharing is achieved by:

  • busbars fed by cables of equal size and length to each battery; or
  • cross (diagonal) connection, taking the positive from one end of the bank and the negative from the other;
  • individual battery protection where the manufacturer requires it;
  • BMS communication connected as the manufacturer specifies.

Battery fuses or breakers should be located as close to the battery as possible. Lugs must suit the conductor and be crimped with the correct tool, terminals tightened to the specified torque with a calibrated tool, and terminal covers refitted.

4.5 AC connections and multiple supplies

Key points

Grid and generator supplies must connect only through approved inverter inputs or an interlocked changeover.

Backed-up loads are normally supplied from a dedicated distribution board.

The neutral–earth arrangement in backup mode must follow the manufacturer's instructions.

In a typical hybrid installation, the grid and often the generator supply the inverter's AC input, and the inverter's AC output supplies a dedicated distribution board for essential loads. Non-essential loads remain on the original board. This limits the inverter to its design load and allows backed-up circuits to be clearly labelled.

Generators must be connected only to the inverter's generator input where provided, or through an approved interlocked changeover. Grid and generator supplies must never be joined, and cables must never be transferred manually between supplies (Module 2, unit 2.11). The generator's output voltage, frequency and stability should be suitable for the inverter.

When the grid is disconnected, the inverter becomes the source for the backed-up circuits, and a correct neutral–earth connection must still exist for RCDs and earthing to function. Some inverters provide this internally in backup mode; others require an external arrangement. The manufacturer's instructions must be followed exactly: a missing link can prevent RCD operation, and an additional link can cause unwanted tripping or current in protective conductors.

On three-phase sites, loads must be balanced and the inverter configuration specified in the design used. A single-phase inverter output must never be connected across two phases.

4.6 Earthing and surge protection

Key points

Earthing must be tested, not assumed.

Earth and bonding connections must be secure and protected from corrosion.

SPD earth conductors must be short and direct.

Earth electrodes should be installed in ground that remains moist where possible, connected with a proper rod clamp and protected in an inspection pit to allow future testing. Electrode resistance must be measured with an earth tester and recorded. Dry, sandy or rocky ground may require longer or multiple electrodes to achieve the value required by the design.

Panel frames and rails are bonded using the mounting system's approved earthing clips or lugs, which penetrate the anodised finish. Inverters, battery racks and distribution boards are connected to the main earthing terminal with protective conductors of the specified size, and continuity is verified (unit 4.8).

DC SPDs are installed at the inverter PV input, and at the array where the design requires it for long cable runs. AC SPDs are installed at the distribution board as specified. SPD earth conductors must be short and straight, since additional length adds voltage during a surge. SPD status indicators should be checked; a device showing an operated indication must be replaced.

4.7 Configuration

Key points

Settings must be taken from the approved design and the documentation for the exact equipment.

Acceptance of a value by the inverter does not confirm that it is correct for the battery.

All settings must be recorded.

Incorrect settings can cause overcharging or undercharging, BMS trips, wasted solar energy or unnecessary generator operation. Settings are taken, in order, from:

  1. the approved design;
  2. the inverter manual for the exact model and firmware;
  3. the battery manufacturer's data and BMS requirements;
  4. both manufacturers' compatibility information;
  5. EcoStride technical instructions where questions remain.

Settings must not be copied from other installations, and lead-acid profiles must not be applied to lithium batteries; for example, equalisation charging used for flooded lead-acid batteries can overcharge lithium cells.

Setting group

Examples

Consequence of error

Battery type and communication

Battery protocol; BMS communication

Inverter operates without battery data; overcharge or premature shutdown

Charge and discharge

Charge and float voltages; maximum charge current; cut-off voltage or SoC

Battery damage, reduced life, nuisance trips, reduced backup

Source priority

Solar first; battery before grid; grid charging

Wasted solar energy, higher costs, unnecessary cycling

Generator

Generator input; charge current; start conditions

Generator overload or excessive fuel use

AC output

Voltage; frequency; backup behaviour

Equipment damage or failure to transfer

Time and monitoring

Date and time; network connection

Incorrect logs; no remote support

Firmware should be checked against the manufacturer's or EcoStride's recommendation before configuration. Final settings are recorded and each settings screen photographed for the job report.

4.8 Inspection and testing

Key points

Inspection and testing are completed before energisation.

Each measurement is compared with an expected value.

All results are recorded.

IEC 62446-1 sets out the inspection and tests to be completed before a PV system is put into service.

Visual inspection confirms that the structure is secure and fixed to supports, penetrations are sealed, cables are supported, protected and labelled, connectors are matched and fully mated, protective devices are of the correct type and rating, earthing and bonding are present, clearances are maintained and warning labels are fitted.

Test

Purpose

Acceptable result

Continuity of protective and bonding conductors

Confirms that exposed metal is connected to earth

Low resistance to the main earthing terminal

Polarity

Prevents reversed connections

Correct polarity on every string and battery connection

String open-circuit voltage

Confirms that each string is complete and correctly connected

Close to the expected value

String current

Confirms that each string produces current

Consistent between identical strings in the same conditions

Insulation resistance

Detects damaged insulation and moisture

Not less than the minimum in the standard or manufacturer's instructions (commonly 1 MΩ)

Earth electrode resistance

Confirms that fault current can flow

Not more than the value required by the design

RCD operation

Confirms that RCDs trip correctly

Trips within the required time at rated current

Terminal torque

Prevents loose connections

Checked and marked at specified torque

String current should be measured with a DC clamp meter during operation or with equipment and a method approved for the purpose. A string must never be short-circuited with a conductor.

Worked example: interpreting string Voc

A string of four modules has a datasheet Voc of 49.6 V and a Voc coefficient of −0.27 %/°C. Cell temperature at the time of measurement is 35 °C, 10 °C above STC. Expected Voc per module is 49.6 × (1 − 0.027) ≈ 48.3 V, and for the string approximately 193 V.

Measured value

Interpretation

190–195 V

Correct

About 145 V

One module's voltage missing: a shorted or bypassed module, or a string of three

About 97 V

One module reversed, subtracting its voltage

0 V

Open circuit: unmated connector, broken conductor, open isolator or blown fuse

Negative value

Reversed polarity at the measurement point

4.9 Commissioning

Key points

Normal operation under one set of conditions does not demonstrate that a system is correctly commissioned.

Energisation follows the manufacturer's sequence.

Baseline readings are recorded for future reference.

The system is energised in the sequence specified by the manufacturer. The display and any abnormal sound or smell are monitored, and energisation is stopped if anything is abnormal.

Each operating mode used by the design is then tested:

  1. PV generation and maximum power tracking;
  2. battery charging from PV, and from grid or generator where designed;
  3. battery supply to loads;
  4. transfer to battery on loss of grid supply, within the specified transfer time;
  5. reconnection on restoration of grid supply;
  6. generator operation, without backfeed to the grid;
  7. operation of the customer's actual loads, including motor starting.

The following are recorded: PV voltage and current per MPPT input; battery voltage, current, SoC and BMS communication status; AC input and output voltage and frequency; and confirmation that monitoring is operational. After a period under load, connections are checked for abnormal temperature using an infrared thermometer or thermal camera where available. These baseline readings form part of the job report and are the reference for future fault-finding.

4.10 Handover

Key points

A job is complete only when the system is tested, recorded, labelled and understood by the customer.

Labels protect everyone who subsequently works on the system.

Outstanding work must be recorded and reported.

Labelling

Durable labels are required to identify each isolator and protective device; to warn that PV conductors remain live in daylight; to warn at the distribution board that circuits may be supplied by the inverter when the grid is off (dual supply); and to state the emergency shutdown sequence at the inverter.

Records

The job report should enable EcoStride to understand the installation without a site visit. It includes photographs of the array, fixings, cable routes, connections, inverter, battery, distribution board, labels and earthing; test results and baseline readings; final settings; serial numbers of principal equipment for warranty purposes; any approved deviation from the design; and any outstanding task with an agreed completion plan.

Customer instruction

The customer is instructed as described in Module 1, unit 1.7, and asked to demonstrate their understanding.

4.11 Common workmanship defects

Key points

Most defects arise from small shortcuts with serious consequences.

Each defect listed below is avoidable.

Defect

Consequence

Correct practice

Fixings into roof sheet only

Array displacement in storms; leaks

Fix into purlins or rafters; seal penetrations

Poorly sealed penetrations

Roof leaks and ceiling damage

Approved washers and outdoor sealant; seal unused holes

Unsupported cables or cables on sharp edges

Insulation damage, earth faults, fire

Clip to structure; protect edges and entries

Mixed-brand PV connectors

Overheating, melting, water ingress

Matched connectors from one manufacturer

Crimps made with pliers or incorrect dies

High-resistance joints; intermittent faults

Correct crimping tool; pull test

Loose battery or AC terminals

Heating, voltage drop, fire

Specified torque with a calibrated tool; mark as checked

AC-only devices on DC circuits

Failure to interrupt DC arcs

DC-rated devices with correct voltage and polarity

Missing or untested earth

Exposed metal live under fault

Install, test and record earthing and bonding

Undersized battery cables

Heat; false low-battery shutdowns

Size for current, length and voltage drop

Unequal parallel battery connections

Uneven ageing of batteries

Busbars, equal cables or cross-connection

Inverter in a hot, enclosed space

Derating and early failure

Ventilated location with specified clearances

Settings copied from another installation

Battery damage; nuisance trips

Settings from the documentation for the exact equipment

Missing labels

Danger to later workers and firefighters

Label all isolators and warnings

Untidy site

Poor customer rating

Leave the site clean

Before reporting a job as complete, the partner should inspect the whole installation as an EcoStride auditor would.

Case studies

The following cases are based on situations commonly encountered on Nigerian sites. Names and places are illustrative.

Case 1: Fixings into sheeting. Several brackets on a 20-module array in Calabar were fixed only into the roof sheet. In the first severe storm a row lifted and tore the sheet, and rain entered the building for a week. Principle: unit 4.2.

Case 2: Mixed connectors. A customer in Benin City reported a burning smell from the roof. A connector formed from two different brands had overheated through contact resistance over eight months and melted. Principle: unit 4.3.

Case 3: Unequal battery connection. A bank of four lithium batteries in Abuja was connected to the inverter at one end only. After a year, the nearest battery's capacity had fallen well below the others and its BMS tripped under heavy load. Principle: unit 4.4.

Case 4: Pre-energisation test. Before energising a system in Ilorin, a partner measured a string Voc of about half the expected value and found one module connected in reverse. The fault was corrected in ten minutes, before any damage occurred. Principle: unit 4.8.

Relationship to performance rating

Rating measure

Relevant units

Quality of workmanship

4.2–4.6, 4.11

Callbacks

4.2, 4.3, 4.7, 4.8

Reporting

4.7, 4.9, 4.10

Customer rating

4.10

Safety-critical conduct

4.6: commissioning without a tested earth is treated as a serious breach

Practical activities

  1. Crimp PV connectors with the correct tool, pull-test them, and section one to inspect the crimp.
  2. On an accessible metal roof, identify the lines of the supporting structure from the fixing pattern.
  3. Practise identifying polarity on a battery or string, including interpreting a reversed reading.
  4. Calculate the expected Voc of a string at the prevailing cell temperature, measure it and compare.
  5. In any hybrid inverter manual, locate the settings for battery type, charge voltage, maximum charge current and source priority.
  6. Inspect an existing installation against the table in unit 4.11 and record each defect and the correct practice.

Glossary

Term

Definition

Baseline readings

Measurements recorded at commissioning for later comparison

Busbar

A rigid conductor to which several cables are connected

Clamping zone

The part of a module frame in which clamps are permitted

Commissioning

Verification that a completed system operates correctly and safely in all modes

Contact resistance

Resistance at a joint between conductors

Cross-connection

Connection of a parallel battery bank with positive and negative taken from opposite ends

Drip loop

A downward loop in a cable before an entry point

Dual supply

A circuit capable of being supplied from more than one source

Equalisation

A controlled overcharge used for flooded lead-acid batteries; harmful to lithium

Galvanic corrosion

Corrosion caused by contact between dissimilar metals in the presence of moisture

Insulation resistance

Resistance between live conductors and earth

Penetration

An opening made through the roof covering

Purlin / rafter

Structural members supporting the roof covering

Torque

Rotational force applied when tightening, measured in N·m

Uplift

Upward wind force acting on modules

Rating
0 0

There are no comments for now.